Placeholder Image

字幕表 動画を再生する

  • - [Narrator] 900 wind turbines will soon cover this stretch

  • of New Mexico Desert, transforming it

  • into the largest wind farm in the Western hemisphere.

  • The project, SunZia Wind, was greenlit in 2006,

  • but it only just received a permit

  • to start construction 17 years later.

  • - Well, we clearly have a problem

  • in how we're permitting projects.

  • - [Narrator] One of the most elusive pieces

  • of green energy projects

  • in the US isn't raw materials, labor, or even money.

  • It's a permit.

  • More than 10,000 energy projects,

  • the vast majority of them wind and solar,

  • were waiting for permission to connect

  • to electric grids at the end of 2022.

  • We'll break down how this decades-long permitting process

  • is becoming a major obstacle for developers

  • and the country's efforts to fight climate change.

  • To understand how the energy permitting process works

  • let's head back to SunZia.

  • Once completed, developers say it will sprawl

  • across three New Mexico counties and supply power

  • to more than three million households

  • in Arizona and California.

  • - It delivers in about 1% of the carbon goals

  • for the country.

  • It's certainly bigger than the Hoover Dam.

  • I wanna share our gratitude to every person

  • and company that's made today's achievement possible.

  • (audience applauding)

  • - [Narrator] Cary Kottler is the Chief Development Officer

  • for Pattern Energy, the company behind SunZia.

  • Developers first applied for federal approval in 2008.

  • Environmental reviews started in 2009.

  • In 2011, the project was fast tracked

  • by the Obama Administration.

  • When the project was conceived

  • the company thought it would receive its permits

  • in about five years.

  • - I don't think anybody goes

  • into a project thinking it'll take 15 years,

  • and so it's had some twists and turns along the way.

  • - [Narrator] Those twists and turns are tied

  • to the local, state and federal permitting systems

  • that can and do get delayed at any stage of the process.

  • - With the SunZia project we really see the complexity,

  • that you have the federal layer

  • and then you have a lot of the local issues.

  • - [Narrator] Sanjay Patnaik is a climate policy researcher

  • at the Brookings Institution think tank.

  • SunZia, like many other renewable energy projects,

  • has faced a range of roadblocks

  • when it comes to local permitting.

  • - Oftentimes delays at the local level can be traced back

  • to the strongest opposition

  • because people feel really strongly

  • about these projects going in their backyard, right?

  • People don't want to give up their land

  • for a transmission line, for instance,

  • to aesthetic reasons, right?

  • People don't want to wind farm right off the coast.

  • - [Narrator] Figuring out whether local regulations allow

  • for development can be tricky.

  • - Let's assume a solar power plant, for instance,

  • that covers multiple municipalities.

  • You will need a permit from all of them

  • and they have very different administrative capacities,

  • different laws on the books.

  • - [Narrator] This process plays out at the state level too.

  • - We also have states that require right of way permits,

  • for instance California, for transmission lines.

  • We have a state where the project is located

  • and then a transmission line goes through a state

  • to another state where the consumers are located.

  • And so that state that is in between

  • doesn't get any of the benefits,

  • that state only gets the costs

  • and oftentimes states are not happy with that.

  • They're trying to avoid that

  • and are trying to put up roadblocks.

  • - [Narrator] But one of the lengthiest parts of the process

  • happens at the federal level.

  • Each federal permit can take years

  • or sometimes as much as a decade to get approved.

  • - The longest is really the right of way permit

  • where the median length is nine years

  • and then we have others,

  • such as Environmental Impact Statement on the NEPA

  • that takes about 3.5 years as a median.

  • - [Narrator] Many of these permits

  • require repetitive paperwork

  • and generate thousands of pages of government analysis.

  • To understand how daunting this process can be,

  • consider a power line.

  • Transmission is crucial for renewable energy projects

  • because the best sites for wind and solar farms

  • are usually far from the cities

  • and industries that consume the most electricity.

  • For SunZia, this means building

  • a 550 mile high voltage power line

  • to transport more than 3,000 megawatts of wind power

  • to Arizona and California.

  • To construct it, developers needed permission

  • from a patchwork of federal, state,

  • local, and tribal agencies.

  • - Citing transmission lines is not an easy thing.

  • You need to take feedback from a lot of different people

  • and that's what we try to do.

  • And sometimes that takes a while.

  • - [Narrator] As a result of negotiations

  • with these stakeholders,

  • SunZia's transmission lines have been rerouted six times.

  • Building transmission lines in the US takes so long,

  • if they are built at all,

  • that it has become a major roadblock

  • for expanding clean energy.

  • (audience applauding) - The SunZia Project

  • is a game changer for America's clean energy economy.

  • - [Narrator] That's why White House officials

  • like Senior Climate Advisor John Podesta

  • are pushing for an overhaul of the permitting process.

  • - We have to increase transmission,

  • high performance interstate transmission by 60%

  • and we have to permit it twice as fast

  • as we've done over the last decade.

  • - [Narrator] After 17 years of regulatory hurdles,

  • Pattern Energy finally broke ground

  • on SunZia in September.

  • It's expected to be fully operational by 2026,

  • meaning the permitting process took more

  • than five times longer

  • than the project's estimated construction timeline.

  • Still, opponents of the SunZia project

  • say the years-long saga

  • can't be blamed on bureaucratic hurdles alone.

  • The project altered part of its route,

  • which also led to delays.

  • - There were a lot of land negotiation issues,

  • especially with the Department of Defense

  • because of a military installation over there

  • that further delayed the project.

  • - [Narrator] And when companies

  • finally get their projects approved,

  • they often face another hurdle.

  • The local grid is at capacity.

  • New wind and solar projects can't be added

  • unless parts of the grid are upgraded

  • and that costs developers money.

  • All of these delays lead some companies

  • to walk away entirely.

  • As time ticks by, rising material costs

  • can destroy a project's viability.

  • Options to buy land expire and customers can lose interest.

  • After years of dramatic growth, large scale solar, wind

  • and battery installations in the US fell 16% in 2022.

  • - It's now law. (audience applauding)

  • - [Narrator] The landmark Climate Bill

  • President Biden signed last year provides $370 billion

  • in subsidies to help make low carbon energy technologies

  • cheaper than fossil fuels.

  • But to keep up with that historic investment,

  • the permitting process will need to speed up.

  • - So the climate goals that the US has set,

  • which is to become Net Zero by 2050

  • and to reduce greenhouse gas emissions by 2030

  • to half of 2005 levels,

  • will not be possible without permitting reform

  • that really speeds up the permitting process

  • for renewable energy projects.

  • - [Narrator] In May, Biden and US lawmakers made another run

  • at streamlining the permitting system

  • with the issue a central topic

  • in negotiations to raise the debt ceiling.

  • The bill includes modest steps to speed up reviews

  • of federal permits

  • under the National Environmental Policy Act,

  • like allowing environmental reviews

  • of multiple projects at a time.

  • - This is not just a federal problem.

  • At the level, there's nimbyism.

  • What we're responsible for

  • are the federal environmental reviews.

  • So trying to get that consolidation,

  • one single set of documents,

  • combining reviews around endangered species

  • with NEPA reviews is really important.

  • - [Narrator] This could offer some help

  • for both fossil fuel and clean energy projects

  • but falls far short of what either party had wanted.

  • - And at the very most senior levels,

  • at the cabinet secretary level, we're meeting

  • on a biweekly basis to look project by project,

  • see where there are challenges

  • but I think that there still needs to be work done,

  • particularly for interstate transmission.

  • - [Narrator] Consolidating

  • the transmission permitting process

  • at the federal level could be one way

  • to reduce these bottlenecks according to a Brookings report.

  • - And that means that individual states

  • cannot put up indefinite roadblocks

  • like we have seen in other projects,

  • and we are proposing to do on the same transmission lines

  • because that central authority from the federal government

  • could really help overcome some of these roadblocks

  • at the state level.

  • - [Narrator] Ultimately, there's no silver bullet solution

  • for fast tracking this permitting process.

  • Policy experts say it will require expansive reform

  • at the local, state and federal levels.

  • (bright music)

- [Narrator] 900 wind turbines will soon cover this stretch

字幕と単語

ワンタップで英和辞典検索 単語をクリックすると、意味が表示されます

B1 中級

Red Tape Is Delaying Thousands of U.S. Energy Projects. Here’s Why. | WSJ(Red Tape Is Delaying Thousands of U.S. Energy Projects. Here’s Why. | WSJ)

  • 20 0
    林宜悉 に公開 2023 年 10 月 05 日
動画の中の単語